Klang Valley Water Cut: Maintenance Work on Schedule, 63% Complete as of 3pm

Air Selangor reports that asset maintenance and replacement work at the Sungai Selangor Phase 1 water treatment plant (SSP1) has reached 63.1% as of Wednesday, June 5, 3pm.

Air Selangor issued a press statement at 3.30pm stating that the work was progressing according to schedule and would be completed by 7pm.

After the works are complete and the main distribution system is stable, water will be delivered to consumers at various stages beginning Thursday morning (June 6).

The duration of the disruption of water supply and recovery of water pressure in the affected area will depend on the location of consumer premises and water pressure at distribution system, it stated.

Air Selangor has said that it expects water supply to recover in the affected area by approximately 20% on Thursday at 3pm, 90% on Friday at 3am and complete recovery at noon on June 7.

The water tankers were also sent to hospitals, clinics and dialysis centers, among others.